Optimizing Workforce for Timely Project Completion: A Comparative Analysis
Optimizing Workforce for Timely Project Completion: A Comparative Analysis
In project management, effective workforce planning is crucial to ensure timely completion of projects. This article provides a comprehensive approach to workforce optimization through the analysis of three case studies. Examination of work duration calculation, the importance of time constraints, and the accurate estimation of required workforce will be discussed through the lens of practical examples.
Case Study 1: The Contractor’s Dilemma
Initial Situation: A contractor undertook to do a certain work in 55 days and employed 48 men. In 11 days, only 1/6 of the work was completed.
Calculating the Remaining Work and Required Workforce
Calculate Remaining Work:Remaining Work Total Work - Work Completed
Remaining Work 5/6 of the Total Work
Calculate Required Workforce:Remaining Time 55 days - 11 days 44 days
Required Workforce Remaining Work × Initial Workforce / Work Completed × Remaining Time
Required Workforce 5/6 × 48 / 1/6 × 44 40 men
Calculate Number of Extra Men Needed:Extra Men Needed Required Workforce - Initial Workforce
Extra Men Needed 40 men - 48 men -8 men
Conclusion: The contractor should reduce the number of workers by 8 men to complete the work on time.
Case Study 2: Complex Workflow Analysis
Initial Situation: 80 people working for 45 days complete 1/4 of the work.
Calculating Total Work and Required Workforce
Calculate Total Work:Total Work 80 workers × 45 days 3600 mandays
Calculate Remaining Work and Required Workforce:Time Constraint: 45 days - 75 days 75 days
Remaining Work 75/14400 mandays 10,800 mandays
Workers Required: 10800/75 144 workers
Already Engaged: 80 workers
Calculate Additional Requirements:Additional Requirements 144 - 80 64 workers
Case Study 3: Mathematical Estimation of Workforce
Initial Situation: 30 men working for 16 days complete 480 mandays, which is 1/3 of the total work.
Calculating Total Work and Additional Workforce Needed
Calculate Total Work:W/3 480 mandays
W 1440 mandays
Calculate Work Remaining and Additional Workforce Needed:2/3 of Total Work 960 mandays
Time Left: 24 days
Required Workforce: 960/24 40 men
Already Engaged: 30 men
Calculate Additional Requirements:Additional Requirements 40 - 30 10 men
Mathematical Analysis and Equations
To optimize the workforce, we can use the given data to set up an equation:
45 days × 80 workers × 1/4 work 75 days × x workers × 1 full work
45 × 80 × 1/4 75x
x 45 × 80 / (4 × 75)
x 192 workers
Conclusion: Without increasing the workforce, the contractor can still meet the deadline with 192 workers.